Cargo trucks and second-carriageway works on the road to the port, illustrating Buenaventura port congestion

Buenaventura’s works now have dates. Your cargo can’t wait until 2028

October 22, 2026

Buenaventura port congestion has been in the headlines for months, with long queues, blockades and full yards. The works meant to fix it are moving ahead with concrete dates, but almost nobody puts them in one place. This article puts them together: what is being built, what is already being corrected at the yards, what is still missing and when it could arrive. Once the dates are on the table, you can decide what to do with your cargo.

The context matters. More than 36% of the country’s imports, in fact, depend on the port’s operation. Cargo also grew 16% to almost 24 million tons, and of the 130 kilometers of road between Buga and the port, 30 were still unfinished, with the first 10 as you approach Buenaventura being the most critical stretch. According to the Sociedad Portuaria Regional (the regional port company), there is no maritime congestion for container ships. In other words, the problem is on land.

What is already being built

On October 1, 2026, work began on the internal alternate road (vía alterna interna). It covers 10 kilometers: 3.5 of upgrades and 6.5 of new second carriageway, with a parking area for tractor-trailers. The Minister of Transport also mentioned a 20-hectare yard with room for about 350 tractor-trailers (mulas) and roughly two years to finish the dual carriageway.

That road is one section of the Buga-Buenaventura corridor, which shows 32.59% progress. Financial close for the last 35 kilometers was confirmed in 2025, and the planned completion date is February 2028. Since the project started in 2006, 2028 is the official target, not a guarantee.

The tunnels are the most delicate part. According to ANI, the national infrastructure agency, the project replaces the electromechanical equipment in the 17 existing tunnels, which add up to 9.3 kilometers, and also builds two new short tunnels of about 1.4 kilometers. The concessionaire estimated that the tunnel works would be in operation between late 2026 and early 2027. That is the company’s estimate, not a date set by ANI. Earlier, in early August, ANI and the concession opened almost 48 kilometers of rehabilitated road. In addition, on October 14 the minister reported that nine of the 21 functional units were unblocked, including the internal alternate road, and that the whole corridor is under construction.

What is already being corrected at the yards and the port

Operational measures are felt sooner than asphalt. For example, the government ordered continuous operation at container yards, the removal of empty containers from external depots and a daily record of movements on the Superintendence of Transport platform. The trucking association reported that empty containers’ time in port fell from 12 days in May to 8 in June.

After the August 10 earthquake, recovery has been uneven. In early September, container operations at SPRBUN had normalized, while TCBUEN still showed high yard utilization and restrictions on some empty container movements. Even so, the manager of the port company described operations as “flowing normally, but congested” because of the pending dual carriageway.

Dredging runs on a separate track

Today the channel is 12.5 meters deep in the inner bay and 13.5 in the outer bay. In March 2026, Invías, the national roads agency, presented the first-phase target: 16.5 and 17.5 meters. At that point the project was still in studies, environmental licensing and prior consultation (consulta previa), with the CONPES document pending, and no start date for the works had been published. Earlier dates had already slipped: in 2024 the plan was to tender by the end of 2025 and have the channel ready in the first half of 2027.

In short, this work determines how large the ships that arrive can be, not how long a truck takes to enter the port.

When Buenaventura port congestion could ease, according to the sources

No agency publishes a single normalization date. Instead, what exists are targets for each project:

  • Existing and new tunnels: between late 2026 and early 2027, according to the concessionaire’s estimate.
  • Internal alternate road with second carriageway: about two years from October 2026, according to the minister.
  • Full Buga-Buenaventura dual carriageway: February 2028, a target set by ANI in 2025.
  • Deepening dredge: no confirmed start date, because in March 2026 it was still in licensing and prior consultation.

Fenix’s take: if the schedules hold, Buenaventura port congestion should ease in stages from late 2026 and through 2027. Structural normality, however, would not arrive before 2028, and dredging is a separate variable.

In the meantime, which cargo can adapt to the market

Not every shipment can switch ports, and it shouldn’t. Three variables decide it: the cargo’s origin and/or final destination, how firm the delivery date is and which carrier the cargo is booked with.

If the cargo is headed to the Valle del Cauca, Buenaventura remains the logical choice because, of the 15.5 million tons moved out of Buenaventura in 2025, more than 7.6 million went to municipalities in the Valle.

Cargo going to or from Antioquia, the Coffee Region or Bogotá

On the other hand, the comparison changes. Puerto Antioquia opened on January 31, 2026, and CMA CGM added it to its PEX2 service with a first call scheduled for October 8, which adds only two transit days compared with Cartagena. The carrier estimates an average distance 43% shorter to Medellín and Bogotá than other northern terminals, and it also expects lower inland costs than through Buenaventura. Moreover, the port has contracts with Maersk, CMA CGM and MSC. After the earthquake, Atlantic coast operations were unaffected.

Still, the alternative is not free of friction: the trucking association identified 14 critical points on the road between the Aburrá Valley and Puerto Antioquia. For this reason, the decision is made with the specific cargo, not with averages. Once a shipment has room on those three variables, it moves from waiting to choosing.

If your cargo stays in Buenaventura

Fenix does not set shipping schedules, because they change with every blockade. The sector reported peaks from Thursday to Sunday and from Wednesday to Friday, with fewer trucks between 7:00 p.m. and 5:00 a.m. But in early September the corridor’s full nighttime closure between 8:00 p.m. and 6:00 a.m. was still in place, and those windows stopped being useful.

What stays stable is the way of operating. The recurring bottleneck is the appointments to return empty containers at one particular terminal, so it makes sense to coordinate the pickup of the full container and the return of the empty as a single operation, with documents ready before the vessel arrives. That daily coordination is part of the job of a freight forwarder present at the port.

Fenix has its own office in Buenaventura and also operates through Puerto Antioquia, Cartagena and Barranquilla, in FCL and LCL, for imports and exports. As a result, ports can be compared with your cargo on the table.

Choosing the right port for your next shipment

Once the dates are in view, the useful question is which port suits each shipment. If you have an import or export to schedule, request a quote and compare Buenaventura with the alternatives using real numbers.

Get a quote for my cargo
Sources consulted

Agencies and companies

ANI — Entraron en funcionamiento 47,98 km de vía rehabilitada en el proyecto 5G Buga-Buenaventura


Invías — Invías lidera socialización de avances del dragado en el puerto de Buenaventura


Sacyr Concesiones — Corredor Buenaventura-Loboguerrero-Buga


Analdex — Carta abierta: situación logística Buenaventura

Roads, works and dredging

Portafolio — ANI inicia construcción de 10 km de vía alterna a Buenaventura para mejorar acceso al puerto


Carreteras Pan-Americanas — Colombia: Inicia la construcción de 10 km de la Vía Alterna Interna a Buenaventura


Semana — Elsa Noguera anunció el inicio de demoliciones para la Vía Alterna Interna a Buenaventura


Pulzo — Tumban casas para darle paso a importante obra: doble calzada estaría lista en 2 años


Radio Nacional — Luego de casi dos décadas de retrasos, la doble calzada Buga-Loboguerrero-Buenaventura estaría lista en 2028


Portafolio — Con cierre financiero, la 5G Buga-Buenaventura avanza pese a líos sociales


Semana — Tras reunión con la minTransporte, alcaldesa de Buenaventura descarta cobro a camiones y prioriza obras para mejorar la conexión del puerto


El País — Dragado del puerto de Buenaventura no avanza y pone en juego la competitividad del país

Port operations and shipping

Infobae — Gobierno y sector portuario anunciaron acciones conjuntas en Buenaventura ante crisis en el puerto


Valora Analitik — Sociedad Portuaria explica las razones por las que colapsó la carga en Buenaventura y las medidas para enfrentarlo


Portafolio — La resolución en veremos: qué está pasando con los contenedores vacíos y la vía al puerto de Buenaventura


RCN Radio — Gobierno ordena operación 24/7 en patios de contenedores de Buenaventura para frenar la congestión


El País — ¿Qué pasa en la vía a Buenaventura? Pasajeros y camioneros reportan eternos trancones diarios


C.H. Robinson — Actualización del mercado de mercancías: septiembre de 2026


El Colombiano — Buenaventura enfrenta colapso por bloqueos: descarga de camiones tarda hasta 24 horas


Container News — CMA CGM adds Puerto Antioquia to revamped PEX2 service


Bloomberg Línea — Las empresas que ya están moviendo carga por Puerto Antioquia: habla su CEO


AJOT — CMA CGM Colombia earthquake operational update


ABC Economía — Defencarga alerta sobre infraestructura vial crítica y bloqueos que amenazan la competitividad de Puerto Antioquia

    Subscribe to our newsletter